Front Avenue Update

Posted on 1st August 2013 at 16:01

Work continues on the Front Avenue Northwest Improvement Project in Castle Rock; this week’s update indicates that construction of new curbs, driveways, ADA ramps and sidewalks is continuing in the area between Shintaffer and A Street Southwest. They’re also working on replacement of stormwater and sewer mains. Next week, demolition of the existing street between Cowlitz Street West and A Street Southwest will get under way. Castle Rock officials say that they anticipate that Front Street Northwest will be closed to vehicular traffic between Shintaffer Street and A Street Southwest. Contact Castle Rock Public Works for other details.