Find us on Facebook!

 

Other Road Work

Posted on 28th July 2014 at 09:03

Work on a water service repair project will have the alley in the 16 hundred block between 22nd and 23rd Avenues closed for the next seven days. Work is scheduled to start at 8 am today between Olympia Way and Maple Street, and should be completed by 8 am on Monday, August 4th. The alley will be closed to through traffic, but local access will be maintained. Use alternate routes to avoid delays.

Cowlitz County continues on its summer road program, with the West Side Highway overlay project getting under way, starting at Beebe Road and continuing to the north. Chip seal operations will move onto roads in the Kelso area, and work on the Headquarters Road Leachate Transmission Project also continues in the area of South Silver Lake Road and Headquarters Road. You’re reminded to slow down for work zones, where fines for violations can be doubled.